BLUF

Data centers: The moratorium starts November 26, but one Severn data center is already asking to add 88,000 square feet. Comments close November 24, and the county's answer will show how far the pause really reaches.

Deals: An Edgewater heating and cooling company just bought the building it works out of for $1.225 million. Oliver Brewing has a new home in Millersville, with a vet clinic and a party rental company down the hall. And Paris Baguette is now open in Crofton.

People: Want a say in how development disputes get decided? All seven Board of Appeals seats are open, and applications are due December 7.

POLICY & ZONING RADAR

Bill 63-26 Pauses New Data Centers. A Severn Expansion Is Still in Play.

A moratorium is days away, and Anne Arundel County's data-center story isn't over.

On November 26, Bill 63-26 takes effect. It puts a 15-month moratorium on new data-center development in Anne Arundel County and repeals the industry's personal-property tax break.

Nine days out, the filing that says the most about the moratorium is an expansion of a data center that has operated for years. Its owner, a San Francisco firm, bought it before the bill existed.

How the county handles it will show developers, lenders and landowners how far the moratorium really reaches, and it will show residents who thought they'd won the fight what they actually won. The bill's text doesn't settle that.

The data center is at 7665 Sandy Farm Rd in Severn, near Route 100 and Telegraph Road, south of BWI. It's a plain, 37-foot-tall building of just over 109,000 square feet on about 50 acres. Oppidan, the developer, has proposed a site plan that would add more than 88,000 square feet, the Baltimore Banner reported on November 10.

The plan also adds a generator yard with 13 generators, air cooling instead of water cooling, and expanded storm drainage to the existing pond.

Oppidan's engineering firm, Kimley-Horn, filed the site plan this fall. At a community meeting on November 9, Kimley-Horn's Jeff Smith said the expansion is needed because demand on the center is growing. The end user hasn't been disclosed. A 2023 report said Amazon occupied part of the building; Amazon did not respond to the Banner.

Public comment on the site plan is open on the county website through November 23rd.

The deed record adds what the news coverage left out. The state property record shows that GI ETS TC Sandy Farms LLC, an entity of San Francisco-based investment firm GI Partners, bought the parcel from Sandy Farms Building LLC on January 29, 2026, for $101,802,291. That was more than eight months before the council passed the bill.

One number going around needs a caution label. In October, Data Center Dynamics reported that Harrison Street had sold two Maryland powered-shell data centers, buildings sold with power and cooling infrastructure already in place, for $221.9 million, and that the Severn property was one of them.

The Ledger's deed check couldn't reconcile that report with the Severn record. The deed names a different seller, and the Severn sale closed in January at $101,802,291. The $221.9 million is a two-property total as Data Center Dynamics reported it. The verified Severn price is the deed's.

A brief reminder of the politics and mechanics of how the bill came to be. Bill 63-26 didn't start as a pause. Republican Councilman Nathan Volke introduced it as an outright ban. Democratic Councilwoman Julie Hummer carried an amendment, at outgoing County Executive Steuart Pittman's request, that turned it into a 15-month moratorium, and it passed 7–0 on October 5, 2026.

As the Ledger reported, the incoming council that inherits the bill includes members on both sides of that ban-versus-pause fight (including Volke and Hummer themselves).

The moratorium runs from November 26, 2026 to January 31, 2028. It also repeals the personal-property tax assessment reduction that qualifying data centers have received, and it creates a work group to recommend permanent regulations before the pause ends.

The pause stops new development: a greenfield data-center project proposed today has no path to approval until the moratorium lapses or permanent rules replace it.

However, according to the Banner's account of the bill, the moratorium doesn't reach centers already in the pipeline or expanding. Sandy Farms fits that exactly: an operating center, owned by a buyer who bought before the bill was introduced, proposing to add about four-fifths of its current footprint while the county's comment window is still open.

Opponents have organized since the meeting. A petition launched November 14, "Stop the Severn Data Center from Doubling: Close the Expansion Moratorium Loophole," asks the county to deny the expansion. Its organizers say only seven people came to the November 9 meeting. Whether that pressure changes anything is up to the county.

The Sandy Farms decision reaches past one parcel. It will show which expansions count as pipeline, how much an incumbent can grow during the pause, and maybe what the work group will be asked to write into permanent rules before January 31, 2028.

Anyone holding land that could host a data center will price it against that answer.

The Ledger will report the county's decision on the site plan when it posts and follow the work group's recommendations as they develop.

THE DEEDBOOK

Cornett Heating & Cooling Buys Its Edgewater Building for $1.225M; Deed Pending

Cornett Heating & Cooling has bought the building it already occupies at 2976 Solomons Island Rd in Edgewater for $1.225 million, according to a release from the brokerage Hyatt Commercial, reported by Patch on November 11. The 2,100-square-foot office building sits on 1.6 acres, zoned for C-2 along Route 2 just south of Annapolis; at the announced price, the sale works out to roughly $583 per square foot - a clean owner-user comp. The property was listed on LoopNet; and a Hyatt release reports multiple offers and a close in under three months; the release does not name the seller, and the broker is quoted only as Gallagher.

Note: the deed hasn't posted to the state's property database yet, so the seller and closing terms are unconfirmed. The Ledger will name the seller and confirm the terms once it records.

RETAIL & FOOD WATCH

Oliver Brewing Has Moved Production to Millersville

Oliver Brewing Co. closed its East Baltimore brewpub in January and began production this spring at 8370 Jumpers Hole Rd in Millersville, the Severna Park Voice reported. The company was founded in 1993 in the basement of what is now Baltimore's Pratt Street Ale House and is owned by Justin Dvorkin and Donald Kelly's 206 Restaurant Group. All of its Baltimore production staff made the move, and 30 to 50 more jobs are planned. "It was right in our backyard, right in the community we live in," Dvorkin told the Voice. He lives in Severna Park; Kelly lives in Arnold.

The buyer, listed in the state record as 8370 Jumpers Holdings LLC and 924 North Clarles LLC, bought the 45,522-square-foot warehouse from Black Water Legacy Trust on September 24, 2024, for $5.5 million, or about $121 per square foot. The assessed improvement value rose from $993,900 to $4,294,300 by January 1, 2025.

Oliver won't be alone in the building. County permits show how it's been divided up.

Oliver's restaurant and taproom take Suite 2 (permit B02441151: 6,972 square feet, $350,000 of work, kitchen and alcohol service) plus a 12,982-square-foot storage suite, 19,954 square feet in all. A facade sign permit was filed November 2.

Tenant improvement permits and a sign out front show who's filling the other suites. Pack Veterinary has Suite 4 (3,200 square feet, active build-out permit), and Absolute Party Rental & Supply is operating from Suite 5. A Center Lane Swim School tenant improvement for Suite 3 (7,182 square feet, two indoor pools) was filed earlier this year and is marked Revision Required.

The taproom, which will have a kitchen, pizza oven, outdoor seating and a banquet room, is targeted for late November or early December. No exact date has been announced, and the brewery wasn't on the November 10 liquor-board docket. Oliver also brews under contract for other Maryland brewers, including Annapolis Beer Co. and Forward Brewing, so the plant serves more of the region's craft-beer business than its own taproom.

It's a solid reuse story: a 1962 warehouse turned into a multi-tenant service center, anchored by a production business whose owners live nearby.

Sources: Severna Park Voice, Nov. 2, 2026; SDAT deed record, 8370 Jumpers Hole Rd; county Land Use Navigator permit records;

Paris Baguette Opens in Crofton

Paris Baguette opened a café November 13 at 1665-A Crofton Center, on the Route 3 corridor, the company announced. Franchisee Sung Park has signed a four-location Maryland area-development agreement. Crofton is his third Maryland café (the first opened in Bethesda) and the brand's eighth in the state, with more sites in development, per the company's release. The release gives no square footage or lease terms. For corridor landlords and brokers, it's another national-brand tenant at Crofton Center and a sign of where franchise money is landing along Route 3.

Source: Paris Baguette release via PR Newswire, Nov. 13, 2026.

PEOPLE & BOARD MOVES

All Seven Board of Appeals Seats Are Open at Once

All seven seats on the county Board of Appeals are open at once, the County Council announced on November 10. The board hears zoning, license, permit and administrative appeals. The turnover is built into the charter: under Section 601, the council appoints seven qualified voters by resolution within 30 days of taking office, members' terms run with the council's, and no more than a majority may belong to one party. Applications are due by 4 p.m. December 7, the day the new government is seated, to [email protected]. Interviews follow at the council's work session Tuesday, December 15, at 10 a.m. at the Arundel Center. For applicants, land-use attorneys and developers, who sits on this board shapes how development disputes get decided. The Ledger will profile the appointees once the council names them.

Source: Anne Arundel County Council release, Nov. 10, 2026; County Charter §601.